BRAGSA is making steady progress on the “Crab Hole” Project in Clare Valley, with works now approximately 90% complete.
The project involves the construction of approximately 514 feet of concrete roadway, together with box and slipper drains to improve drainage, accessibility, and the overall resilience of the roadway.
Additional works are scheduled to complete the remaining sections of the road and drainage infrastructure, ensuring the project delivers a safe, durable, and reliable roadway for residents and road users.
This initiative forms part of BRAGSA’s Community Improvement Project (CIP), which is dedicated to enhancing communities through infrastructure improvements that strengthen connectivity, improve safety, and enhance accessibility across St. Vincent and the Grenadines.