A progress report on the construction of the Arnos Vale Acute Care Hospital (AVAC) was presented to Parliament by the Minister of Health Daniel Cummings.
Responding to queries from Senator Peters, the Minister detailed that the project is funded through a US$125 million (EC$339.6 million) loan from the Republic of China (Taiwan) under the Strengthening Health Resilience Project. Construction commenced in December 2024 with an original target completion date of August 2027.
Total expenditure on the project to date stands at approximately EC$58 million, which includes EC$32.89 million in stored equipment and building supplies. Physical construction progress is estimated at 15 percent, following a significant slowdown in work after the 2025 general elections.
The Minister indicated that a revised completion timeline and cost estimate will be established once ongoing discussions with the project contractor and consultant are resolved. The Minister affirmed government policy that Arnos Vale will serve as the country’s primary hospital facility, with no further hospital expansion planned for Milton Cato Memorial Hospital.